After allowing the writing of the attribute 2 of the special day table object (ID = 11) from the server example 2.
The GX DLMS Director was supposed to let us add and remove special day date in the array. However, the two buttons (Add and Remove) responsible of these actions were still unreachable (check uploaded picture), we are no able to test.
Special Day Table object
Hi,
Days are removed and inserted using actions, not write. Check your access level for actions #1 and #2.
I'll close this.
BR,
Mikko
Hi,
Hi,
You are right, when i changed the access level of these two methods, the two buttons became accessible.
However, in the server side (DLMS.c server example 2) the two methods "Add" and "Remove" are not implemented yet.
I will open a feature request about the implementation of these methods.
Best regards,
Lara Wakim